Once almost down the central heating pipes were put in these would carry the flow and return from the boilers to the radiators and underfoot heating system. We then put down reinforcing mesh to tie the under floor heating pipes to this would prevent them floating in the cement. The heating pipe is Hep2o pipe supplied by "Real Heating" it is the 20mm under floor heating pipe we laid a total of 450 meters in 6 separate circuits Once complete we contacted our concrete supplier who visited the site before he arrived with the cement mixer to check access and equipment required. |